Chapter 50 — Flood Prevention and Drainage
Purpose and intent.
Sec. 50-71. Purpose and intent.
The purpose of this article is to protect, maintain and enhance the public health, safety, environment and general welfare and to minimize public and private losses due to flood conditions in flood hazard areas, as well as to protect the beneficial uses of floodplain areas for water quality protection, streambank and stream corridor protection, wetlands preservation and ecological and environmental protection by provisions designed to:
Applicability.
Sec. 50-72. Applicability.
This article shall be applicable to all areas within the city. (Ord. No. 2006-28, § 1.2, 2-2-2006; Ord. No. 2018-17, § 1, 7-15-2019)
Designation of article administrator.
Sec. 50-73. Designation of article administrator.
The public works department is hereby appointed to administer and implement the provisions of this article. (Ord. No. 2006-28, § 1.3, 2-2-2006)
Basis for area of special flood hazard—Flood area maps and studies.
Sec. 50-74. Basis for area of special flood hazard—Flood area maps and studies.
For the purposes of this article, the following are adopted by reference:
Compatibility with other regulations.
Sec. 50-75. Compatibility with other regulations.
This article is not intended to modify or repeal any other ordinance, rule, regulation, statute, easement, covenant, deed restriction or other provision of law. The requirements of this article are in addition to the requirements of any other ordinance, rule, regulation or other provision of law, and where any provision of this article imposes restrictions different from those imposed by any other ordinance, rule, regulation or other provision of law, whichever provision is more restrictive or impose higher protective standards for human health or the environment shall control. (Ord. No. 2006-28, § 1.5, 2-2-2006)
Severability.
Sec. 50-76. Severability.
If the provisions of any section, subsection, paragraph, subdivision or clause of this article shall be adjudged invalid by a court of competent jurisdiction, such judgment shall not affect or invalidate the remainder of any section, subsection, paragraph, subdivision or clause of this article. (Ord. No. 2006-28, § 1.6, 2-2-2006)
Warning and disclaimer of liability.
Sec. 50-77. Warning and disclaimer of liability.
The degree of flood protection required by this article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur; flood heights may be increased by man-made or natural causes. This article does not imply that land outside the areas of special flood hazard or uses permitted within such areas will be free from flooding or flood damages. This article shall not create liability on the part of the city or by any officer or employee thereof for any flood damages that result from reliance on this article or any administrative decision lawfully made there under. (Ord. No. 2006-28, § 1.7, 2-2-2006)
Definitions.
Sec. 50-78. Definitions.
[The following words, terms and phrases, when used in this article, shall have the meanings ascribed to them in this section, except where the context clearly indicates a different meaning:]
"Addition (to an existing building)" means any walled and roofed expansion to the perimeter of a building in which the addition is connected by a common load-bearing wall other than a fire wall. Any walled and roofed addition which is con-nected by a fire wall or is separated by an independent perimeter load-bearing wall shall be considered new construction.
"Appeal" means a request for a review of the building official's interpretation of any provision of this article.
"Area of shallow flooding" means a designated AO or AH Zone on a community's flood insurance rate map (FIRM) with base flood depths from one to three feet, and/or where a clearly defined channel does not exist, where the path of flooding is unpredictable and indeterminate, and where velocity flow may be evident.
"Area of special flood hazard" is the land subject to a one percent or greater chance of flooding in any given year. This includes all floodplain and flood prone areas at or below the base flood elevation (including A, A1—30, A-99, AE, AO, AH, and AR on the FHBM or the FIRM), all floodplain and flood prone areas at or below the future-conditions flood elevation, and all other flood prone areas as referenced in section 50-74. All streams with a drainage area of 100 acres or greater shall have the area of special flood hazard delineated.
"Base flood" means the flood having a one percent chance of being equaled or exceeded in any given year, also known as the 100-year flood.
"Base flood elevation" means the highest water surface elevation anticipated at any given point during the base flood.
"Basement" means that portion of a building having its floor subgrade (below ground level) on all sides.
"Building" means any structure built for support, shelter, or enclosure for any occupancy or storage.
"Development" means any man-made change to improved or unimproved real estate including but not limited to buildings or other structures, mining, dredging, filling, clearing, grubbing, grading, paving, any other installation of impervious cover, excavation or drilling operations or storage of equipment or materials.
"Elevated building" means a non-basement building built to have the lowest floor of the lowest enclosed area elevated above the ground level by means of fill, solid foundation perimeter walls, pilings, columns, piers, or shear walls adequately anchored so as not to impair the structural integrity of the building during a base flood event.
"Existing construction" means any structure for which the "start of construction" commenced before March 14, 1974 [*i.e., the effective date of the FIRST floodplain management code or ordinance adopted by the community as a basis for that community's participation in the National Flood Insurance Program (NFIP)].
"Existing manufactured home park or subdivision" means a manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum the installation of utilities, the construction of streets, and final site grading or the pouring of concrete pads) is completed before March 14, 1974 [*i.e., the effective date of the FIRST floodplain management regulations adopted by a community].
"Expansion to an existing manufactured home park or subdivision" means the preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed, including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads.
"FEMA" means the Federal Emergency Management Agency.
"Flood" or "flooding" means a general and temporary condition of partial or complete inundation of normally dry land areas from:
"Flood hazard boundary map" or "FHBM" means an official map of a community, issued by the Federal Insurance Administration, where the boundaries of areas of special flood hazard have been defined as Zone A.
"Flood insurance rate map" or "FIRM" means an official map of a community, issued by the Federal Insurance Administration, delineating the areas of special flood hazard and/or risk premium zones applicable to the community.
"Flood insurance study" or "FIS" means the official report by the Federal Insurance Administration evaluating flood hazards and containing flood profiles and water surface elevations of the base flood.
"Floodplain" means any land area susceptible to flooding.
"Floodproofing" means any combination of structural and non-structural additions, changes, or adjustments to structures which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.
"Floodway" or "regulatory floodway" means the channel of a stream or other watercourse and the adjacent areas of the floodplain which is necessary to contain and discharge the base flood flow without cumulatively increasing the base flood elevation more than one foot.
"Functionally dependent use" means a use which cannot perform its intended purpose unless it is located or carried out in close proximity to water.
"Future conditions flood" means the flood having a one percent chance of being equaled or exceeded in any given year based on future-conditions hydrology. Also known as the 100-year future-conditions flood.
"Future-conditions flood elevation" means the flood standard equal to or higher than the base flood elevation. The future-conditions flood elevation is defined as the highest water surface anticipated at any given point during the future-conditions flood.
"Future-conditions floodplain" means any land area susceptible to flooding by the future-conditions flood.
"Future-conditions hydrology" means the flood discharges associated with projected land-use conditions based on a community's zoning map, comprehensive land-use plans, and/or watershed study projections, and without consideration of projected future construction of flood detention structures or projected future hydraulic modifications within a stream or other waterway, such as bridge and culvert construction, fill, and excavation.
"Highest adjacent grade" means the highest natural elevation of the ground surface, prior to construction, adjacent to the proposed foundation of a building.
"Lowest floor" means the lowest floor of the lowest enclosed area, including basement. An unfinished or flood resistant enclosure, used solely for parking of vehicles, building access, or storage, in an area other than a basement, is not considered a building's lowest floor, provided that such enclosure is not built so as to render the structure in violation of other provisions of this article.
"Manufactured home" means a building, transportable in one or more sections, built on a permanent chassis and designed to be used with or without a permanent foundation when connected to the required utilities. The term includes any structure commonly referred to as a "mobile home" regardless of the date of manufacture. The term also includes parked trailers, travel trailers and similar transportable structures placed on a site for 180 consecutive days or longer and intended to be improved property.
"Mean sea level" means the average height of the sea for all stages of the tide. It is used as a reference for establishing various elevations within the floodplain. For purposes of this article the term is synonymous with National Geodetic Vertical Datum (NGVD) and/or the North American Vertical Datum (NAVD) of 1988.
"National Geodetic Vertical Datum (NGVD)" as corrected in 1929 is a vertical control used as a reference for establishing varying elevations within the floodplain.
"New construction" means any structure (see definition) for which the "start of construction" commenced after March 14, 1974 and includes any subsequent improvements to the structure. [* i.e., the effective date of the FIRST floodplain management ordinance adopted by the community as a basis for community participation in the (NFIP)].
"New manufactured home park or subdivision" means a manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after Marsh 14, 1974 [*i.e., the effective date of the first floodplain management regulations adopted by a community].
"North American Vertical Datum (NAVD) of 1988" is a vertical control used as a reference for establishing varying elevations within the floodplain.
"Owner" means the legal or beneficial owner of a site, including but not limited to, a mortgagee or vendee in possession, receiver, executor, trustee, lessee or other person, firm or corporation in control of the site.
"Permit" means the permit issued by the Acworth Public Works Department or Acworth Building Department to the applicant which is required prior to undertaking any development activity.
"Repetitive loss" means flood-related damages sustained by a structure on two separate occasions during a 10-year period for which the cost of repairs at the time of each such flood event, on the average, equals, or exceeds 25 percent of the market value of the structure before the damage occurred.
"Site" means the parcel of land being developed, or the portion thereof on which the development project is located.
"Start of construction" means the date the permit was issued, provided the actual start of construction, repair, reconstruction, or improvement was within 180 days of the permit date. The actual start means the first placement of permanent construction of the structure such as the pouring of slabs or footings, installation of piles, construction of columns, or any work beyond the stage of excavation, and includes the placement of a manufactured home on a foundation. Perma-nent construction does not include initial land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms; nor does it include the installation on the property of buildings appurtenant to the permitted structure, such as garages or sheds not occupied as dwelling units or part of the main structure. (Note: Accessory structures are not exempt from any ordinance requirements). For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
"Structure" means a walled and roofed building that is principally above ground, a manufactured home, a gas or liquid storage tank.
"Subdivision" means the division of a tract or parcel of land resulting in one or more new lots or building sites for the purpose, whether immediately or in the future, of sale, other transfer of ownership or land development, and includes divisions of land resulting from or made in connection with the layout or development of a new street or roadway or a change in an existing street or roadway.
"Substantial damage" means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.
"Substantial improvement" means any combination of repairs, reconstruction, alteration, or improvements to a structure, taking place during a 10-year period, in which the cumulative cost equals or exceeds 50 percent of the market value of the structure before the "start of construction" of the improvement. Note: The market value of the building should be (1) the appraised value of the structure prior to the start of the initial repair or improvement, or (2) in the case of damage, the value of the structure prior to the damage occurring. This term includes structures, which have incurred "repetitive loss" or "substantial dam-age", regardless of the actual amount of repair work performed. The term does not, however, include either:
For the purposes of this definition, "substantial improvement" is considered to occur when the first alteration of any wall, ceiling, floor, or other structural part of the structure commences, whether or not that alteration affects the external dimensions of the structure.
"Substantially improved existing manufactured home park or subdivision" is where the repair, reconstruction, rehabilitation or improvement of the streets, utilities and pads equals or exceeds 50 percent of the value of the streets, utilities and pads before the repair, reconstruction or improvement commenced.
"Variance" is a grant of relief from the requirements of this article which permits construction in a manner otherwise prohibited by this article.
"Violation" means the failure of a structure or other development to be fully compliant with the community's floodplain management regulations. A structure or other development without the elevation certificate, other certificates, or other evidence of compliance required in this article is presumed to be in violation until such time as that documentation is provided. (Ord. No. 2006-28, § 2, 2-2-2006)
Variance procedures.
Sec. 50-79. Variance procedures.
The following variance and appeals procedures shall apply to an applicant who has been denied a permit for a development activity, or to an owner or developer who has not applied for a permit because it is clear that the proposed development activity would be inconsistent with the provisions of this article. A request for a variance may be submitted by an applicant who has been denied a permit by the public works department, or by an owner or developer who has not previously applied for a permit for the reasons stated herein above.
Violations, enforcement and penalties.
Sec. 50-80. Violations, enforcement and penalties.
Any action or inaction which violates the provisions of this article or the requirements of an approved stormwater management plan or permit, may be subject to the enforcement actions outlined in this section. Any such action or inaction which is continuous with respect to time is deemed to be a public nuisance and may be abated by injunctive or other equitable relief. The imposition of any of the penalties described below shall not prevent such equitable relief.
Secs. 50-81—50-84. Reserved.
Permit application requirements.
Sec. 50-85. Permit application requirements.
No owner or developer shall perform any development activities on a site where an area of special flood hazard is located without first meeting the requirements of this article prior to commencing the proposed activity.
Unless specifically excluded by this article, any landowner or developer desiring a permit for a development activity shall submit to the public works department a permit application on a form provided by the public works department for that purpose.
No permit will be approved for any development activities that do not meet the requirements, restrictions and criteria of this article. (Ord. No. 2006-28, § 3.1, 2-2-2006)
Floodplain management plan requirements.
Sec. 50-86. Floodplain management plan requirements.
An application for a development project with any area of special flood hazard located on the site will be required to include a floodplain management/flood damage prevention plan. This plan shall include the following items:
The approved floodplain management/flood damage prevention plan shall contain certification by the applicant that all development activities will be done according to the plan or previously approved revisions. Any and all development permits and/or use and occupancy certificates or permits may be revoked at any time if the construction and development activities are not in strict accordance with approved plans. (Ord. No. 2006-28, § 3.2, 2-2-2006)
Construction stage submittal requirements.
Sec. 50-87. Construction stage submittal requirements.
For all new construction and substantial improvements on sites with a floodplain management/ flood damage prevention plan, the permit holder shall provide to the building department a certified as-built elevation certificate or floodproofing certificate for non-residential construction including the lowest floor elevation or flood-proofing level immediately after the lowest floor or floodproofing is completed. A final elevation certificate shall be provided after completion of construction including final grading of the site. Any lowest floor certification made relative to mean sea level shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same. When floodproofing is utilized for non-residential structures, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same.
Any work undertaken prior to approval of these certifications shall be at the permit holder's risk. The building department shall review the above referenced certification data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further work being allowed to proceed. Failure to submit certification or failure to make the corrections required hereby shall be cause to issue a stop work order for the project. (Ord. No. 2006-28, § 3.3, 2-2-2006)
Duties and responsibilities of the administrator.
Sec. 50-88. Duties and responsibilities of the administrator.
Duties of the public works department shall include, but shall not be limited to:
Secs. 50-89, 50-90. Reserved.
Definition of floodplain boundaries.
Sec. 50-91. Definition of floodplain boundaries.
Definition of floodway boundaries.
Sec. 50-92. Definition of floodway boundaries.
The width of a floodway shall be determined from the FIS or FEMA approved flood study. For all streams with a drainage area of 100 acres or greater, the regulatory floodway shall be provided by the public works department. If floodway data is not available from the public works department, then it shall be determined by a registered professional engineer using a method approved by FEMA and the public works department. (Ord. No. 2006-28, § 4.2, 2-2-2006)
General standards.
Sec. 50-93. General standards.
Engineering study requirements for floodplain encroachments.
Sec. 50-94. Engineering study requirements for floodplain encroachments.
An engineering study is required, as appropriate to the proposed development activities on the site, whenever a development proposes to disturb any land within the future-conditions floodplain, except for a residential single-lot development on streams without established base flood elevations and/or floodways for which the provisions of section 50-104 apply. This study shall be prepared by a currently registered professional engineer in the State of Georgia and made a part of the application for a permit. This information shall be submitted to and approved by the public works department prior to the approval of any permit which would authorize the disturbance of land located within the future-conditions floodplain. Such study shall include:
Floodway encroachments.
Sec. 50-95. Floodway encroachments.
Located within areas of special flood hazard are areas designated as floodway. A floodway may be an extremely hazardous area due to velocity flood waters, debris or erosion potential. In addition, floodways must remain free of encroachment in order to allow for the discharge of the base flood without increased flood heights. Therefore the following provisions shall apply:
Maintenance requirements.
Sec. 50-96. Maintenance requirements.
The property owner shall be responsible for continuing maintenance as may be needed within an altered or relocated portion of a floodplain on his property so that the flood-carrying or flood storage capacity is not diminished. The public works department may direct the property owner (at no cost to the city) to restore the flood-carrying or flood storage capacity of the floodplain if the owner has not performed maintenance as required by the approved floodplain management plan on file with the public works department. (Ord. No. 2006-28, § 4.6, 2-2-2006)
Secs. 50-97—50-100. Reserved.
General standards.
Sec. 50-101. General standards.
In all areas of special flood hazard the following provisions apply:
Building standards for
Sec. 50-102. Building standards for structures and buildings within the future-conditions floodplain.
The following provisions, in addition to those in section 50-101, shall apply:
The structure, together with attendant utility and sanitary facilities, must be designed to be watertight to one foot above the base flood elevation, or at least as high as the future-conditions flood elevation, whichever is higher, with walls substantially impermeable to the passage of water and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the building department.
Building standards for structures and buildings authorized adjacent to the future-conditions floodplain.
Sec. 50-103. Building standards for structures and buildings authorized adjacent to the future-conditions floodplain.
Building standards for residential single-lot developments on streams without established base flood elevations and/or floodway (A-Zones).
Sec. 50-104. Building standards for residential single-lot developments on streams without established base flood elevations and/or floodway (A-Zones).
For a residential single-lot development not part of a subdivision that has areas of special flood hazard, where streams exist but no base flood data have been provided (A-Zones), the building department shall review and reasonably utilize any available scientific or historic flood elevation data, base flood elevation and floodway data, or future-conditions flood elevation data available from a federal, state, local or other source, in order to administer the provisions and standards of this article.
If data are not available from any of these sources, the following provisions shall apply:
Building standards for areas of shallow flooding (AO-Zones).
Sec. 50-105. Building standards for areas of shallow flooding (AO-Zones).
Areas of special flood hazard may include designated "AO" shallow flooding areas. These areas have base flood depths of one to three feet above ground, with no clearly defined channel. In these areas the following provisions apply:
Standards for subdivisions.
Sec. 50-106. Standards for subdivisions.
Secs. 50-107—50-110. Reserved.
General provisions.
Sec. 50-111. General provisions.
The following activities are exempt from this article, unless otherwise determined by the city:
Definitions.
Sec. 50-112. Definitions.
The following words, terms and phrases, when used in this article, shall have the meanings ascribed to them in this section, except where the context clearly indicates a different meaning:
Applicant means a person submitting a post-development stormwater management application and plan for approval.
Channel means a natural or artificial watercourse with a definite bed and banks that conducts continuously or periodically flowing water.
Conservation easement means an agreement between a land owner and the City of Acworth or other government agency or land trust that permanently protects open space or greenspace on the owner's land by limiting the amount and type of development that can take place, but continues to leave the remainder of the fee interest in private ownership.
Detention means the temporary storage of stormwater runoff in a stormwater management facility for the purpose of controlling the peak discharge.
Detention facility means a detention basin or structure designed for the detention of stormwater runoff and gradual release of stored water at controlled rates.
Developer means a person who undertakes land development activities.
Development means a land development or land development project.
Drainage easement means an easement appurtenant or attached to a tract or parcel of land allowing the owner of adjacent tracts or other persons to discharge stormwater runoff onto the tract or parcel of land subject to the drainage easement.
Erosion and sedimentation control plan means a plan that is designed to minimize the accelerated erosion and sediment runoff at a site during land disturbance activities.
Extended detention means the detention of stormwater runoff for an extended period, typically 24 hours or greater.
Extreme flood protection means measures taken to prevent adverse impacts from large lowfrequency storm events with a return frequency of 100 years or more.
Flooding means a volume of surface water that is too great to be confined within the banks or walls of a conveyance or stream channel and that overflows onto adjacent lands.
Greenspace or open space means permanently protected areas of the site that are preserved in a natural state.
Hotspot means an area where the use of the land has the potential to generate highly contaminated runoff, with concentrations of pollutants in excess of those typically found in stormwater.
Hydrologic soil group (HSG) means a natural resource conservation service classification system in which soils are categorized into four runoff potential groups. The groups range from group A soils, with high permeability and little runoff produced, to group D soils, which have low permeability rates and produce much more runoff.
Impervious cover means a surface composed of any material that significantly impedes or prevents the natural infiltration of water into soil. Impervious surfaces include, but are not limited to, rooftops, buildings, streets and roads, and any concrete or asphalt surface.
Industrial stormwater permit means a National Pollutant Discharge Elimination System (NPDES) permit issued to an industry or group of industries, which regulates the pollutant levels associated with industrial stormwater discharges or specifies on-site pollution control strategies.
Infiltration means the process of percolating stormwater runoff into the subsoil.
Jurisdictional wetland means an area that is inundated or saturated by surface water or groundwater at a frequency and duration sufficient to support a prevalence of vegetation typically adapted for life in saturated soil conditions, commonly known as hydrophytic vegetation.
Land development means any land change, including, but not limited to, clearing, digging, grubbing, stripping, removal of vegetation, dredging, grading, excavating, transporting and filling of land, construction, paving, and any other installation of impervious cover.
Land development activities means those actions or activities that comprise, facilitate or result in land development.
Land development project means a discrete land development undertaking.
Inspection and maintenance agreement means a written agreement providing for the long-term inspection and maintenance of stormwater management facilities and practices on a site or with respect to a land development project, which when properly recorded in the deed records constitutes a restriction on the title to a site or other land involved in a land development project.
New development means a land development activity on a previously undeveloped site.
Nonpoint source pollution means a form of water pollution that does not originate from a discrete point such as a sewage treatment plant or industrial discharge, but involves the transport of pollutants such as sediment, fertilizers, pesticides, heavy metals, oil, grease, bacteria, organic materials and other contaminants from land to surface water and groundwater via mechanisms such as precipitation, stormwater runoff, and leaching. Nonpoint source pollution is a by-product of land use practices such as agricultural, silvicultural, mining, construction, subsurface disposal and urban runoff sources.
Nonstructural stormwater management practice or nonstructural practice means any natural or planted vegetation or other nonstructural component of the stormwater management plan that provides for or enhances stormwater quantity and/or quality control or other stormwater management benefits, and includes, but is not limited to, riparian buffers, open and greenspace areas, overland flow filtration areas, natural depressions, and vegetated channels.
Off-site facility means a stormwater management facility located outside the boundaries of the site.
On-site facility means a stormwater management facility located within the boundaries of the site.
Overbank flood protection means measures taken to prevent an increase in the frequency and magnitude of out-of-bank flooding (i.e. flow events that exceed the capacity of the channel and enter the floodplain), and that are intended to protect downstream properties from flooding for the 2-year through 25-year frequency storm events.
Owner means the legal or beneficial owner of a site, including but not limited to, a mortgagee or vendee in possession, receiver, executor, trustee, lessee or other person, firm or corporation in control of the site.
Permit means the permit issued by the city to the applicant which is required for undertaking any land development activity.
Person means, except to the extent exempted from this article, any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, city, county or other political subdivision of the state, any interstate body or any other legal entity.
Post-development refers to the time period, or the conditions that may reasonably be expected or anticipated to exist, after completion of the land development activity on a site as the context may require.
practicability policy means the latest edition of the Metropolitan North Georgia Water Planning District's Policy on Practicability Analysis for Runoff Reduction.
Pre-development refers to the time period, or the conditions that exist, on a site prior to the commencement of a land development project and at the time that plans for the land development of a site are approved by the plan approving authority. Where phased development or plan approval occurs (preliminary grading, roads and utilities, etc.), the existing conditions at the time prior to the first item being approved or permitted shall establish pre-development conditions.
Project means a land development project.
Redevelopment means a land development project on a previously developed site, but excludes ordinary maintenance activities, remodeling of existing buildings, resurfacing of paved areas, and exterior changes or improvements which do not materially increase or concentrate stormwater runoff, or cause additional nonpoint source pollution.
Regional stormwater management facility or regional facility means stormwater management facilities designed to control stormwater runoff from multiple properties, where the owners or developers of the individual properties may assist in the financing of the facility, and the requirement for on-site controls is either eliminated or reduced.
Runoff means stormwater runoff.
Site means the parcel of land being developed, or the portion thereof on which the land development project is located.
Stormwater better site design means nonstructural site design approaches and techniques that can reduce a site's impact on the watershed and can provide for nonstructural stormwater management.
Stormwater better site design includes conserving and protecting natural areas and greenspace, reducing impervious cover and using natural features for stormwater management.
Stormwater management means the collection, conveyance, storage, treatment and disposal of stormwater runoff in a manner intended to prevent increased flood damage, streambank channel erosion, habitat degradation and water quality degradation, and to enhance and promote the public health, safety and general welfare.
Stormwater management facility means any infrastructure that controls or conveys stormwater runoff.
Stormwater management measure means any stormwater management facility or nonstructural stormwater practice.
Stormwater management plan means a document describing how existing runoff characteristics will be affected by a land development project and containing measures for complying with the provisions of this article.
Stormwater management system means the entire set of structural and nonstructural stormwater management facilities and practices that are used to capture, convey and control the quantity and quality of the stormwater runoff from a site.
Stormwater retrofit means a stormwater management practice designed for a currently developed site that previously had either no stormwater management practice in place or a practice inadequate to meet the stormwater management requirements of the site.
Stormwater runoff means the flow of surface water resulting from precipitation.
Structural stormwater control means a structural stormwater management facility or device that controls stormwater runoff and changes the characteristics of that runoff including, but not limited to, the quantity and quality, the period of release or the velocity of flow of such runoff.
Subdivision means the division of a tract or parcel of land resulting in one or more new lots or building sites for the purpose, whether immediately or in the future, of sale, other transfer of ownership or land development, and includes divisions of land resulting from or made in connection with the layout or development of a new street or roadway or a change in an existing street or roadway. (Ord. No. 2020-35, § 1, 12-17-2020)
Permit procedures and requirements.
Sec. 50-113. Permit procedures and requirements.
Unless otherwise exempted by this article, a permit application shall be accompanied by the following items in order to be considered:
To accomplish this goal the following information shall be included in the concept plan, which shall be submitted in advance of the meeting:
Local watershed plans, the city's greenspace projection plan, and any relevant resource protection plans will be consulted in the discussion of the concept plan.
This plan shall be in accordance with the criteria established in this section and must be submitted with the stamp and signature of a professional engineer (PE) licensed in the State of Georgia, who must verify that the design of all stormwater management facilities and practices meet the submittal requirements outlined in the submittal checklist(s) found in the stormwater design manual.
The stormwater management plan must ensure that the requirements and criteria in this article are being complied with and that opportunities are being taken to minimize adverse post-development stormwater runoff impacts from the development. The plan shall consist of maps, narrative, and supporting design calculations (hydrologic and hydraulic) for the proposed stormwater management system. The plan shall include all of the information required in the stormwater management site plan checklist found in the stormwater design manual. This includes:
The inspection and maintenance agreement, if applicable, must be approved by the city prior to plan approval, and recorded in the deed records upon final plat approval.
The inspection and maintenance agreement shall identify by name or official title the person(s) responsible for carrying out the inspection and maintenance. Responsibility for the operation and maintenance of the stormwater management facility or practice, unless assumed by a governmental agency, shall remain with the property owner and shall pass to any successor owner. If portions of the land are sold or otherwise transferred, legally binding arrangements shall be made to pass the inspection and maintenance responsibility to the appropriate successors in title. These arrangements shall designate for each portion of the site, the person to be permanently responsible for its inspection and maintenance.
As part of the inspection and maintenance agreement, a schedule shall be developed for when and how often routine inspection and maintenance will occur to ensure proper function of the stormwater management facility or practice. The agreement shall also include plans for annual inspections to ensure proper performance of the facility between scheduled maintenance and shall also include remedies for the default thereof.
In addition to enforcing the terms of the inspection and maintenance agreement, the city may also enforce all of the provisions for ongoing inspection and maintenance in section 50-116 of this article.
A stormwater management plan must be submitted to the city, which shows the adequacy of the off-site or regional facility.
To be eligible for a modification, the applicant must demonstrate to the satisfaction of the city that the use of an off-site or regional facility will not result in the following impacts to upstream or downstream areas:
Post-development stormwater management performance criteria.
Sec. 50-114. Post-development stormwater management performance criteria.
The following performance criteria shall be applicable to all stormwater management plans, unless otherwise provided for in this article:
Stormwater runoff quality/reduction: Stormwater Runoff Quality/Reduction shall be provided by using the following:
Applicants shall consult the Georgia Stormwater Management Manual for guidance on the factors that determine site design feasibility when selecting and locating a structural stormwater control.
Construction inspections of post-development stormwater management system.
Sec. 50-115. Construction inspections of post-development stormwater management system.
All inspections shall be documented with written reports that contain the following information:
If any violations are found, the applicant shall be notified in writing of the nature of the violation and the required corrective actions.
Ongoing inspection and maintenance of stormwater facilities and practices.
Sec. 50-116. Ongoing inspection and maintenance of stormwater facilities and practices.
A stormwater management facility or practice shall be inspected on a periodic basis, by the responsible person, in accordance with the approved inspection and maintenance agreement. In the event that the stormwater management facility has not been maintained and/or becomes a danger to public safety or public health, the city shall notify the person responsible for carrying out the maintenance plan by registered or certified mail to the person specified in the inspection and maintenance agreement. The notice shall specify the measures needed to comply with the agreement and the plan and shall specify the time within which such measures shall be completed. If the responsible person fails or refuses to meet the requirements of the inspection and maintenance agreement, the city, may correct the violation as provided in paragraph (d) hereof.
Inspection programs by the city may be established on any reasonable basis, including but not limited to: routine inspections; random inspections; inspections based upon complaints or other notice of possible violations; and joint inspections with other agencies inspecting under environmental or safety laws. Inspections may include, but are not limited to: reviewing maintenance and repair records; sampling discharges, surface water, groundwater, and material or water in stormwater management facilities; and evaluating the condition of stormwater management facilities and practices.
Violations, enforcement and penalties.
Sec. 50-117. Violations, enforcement and penalties.
Any action or inaction which violates the provisions of this article or the requirements of an approved stormwater management plan or permit, may be subject to the enforcement actions outlined in this section. Any such action or inaction, which is continuous with respect to time, is deemed to be a public nuisance and may be abated by injunctive or other equitable relief. The imposition of any of the penalties described below shall not prevent such equitable relief. The imposition of any of the penalties described below shall not prevent such equitable relief:
General provisions.
Sec. 50-118. General provisions.
Definitions.
Sec. 50-119. Definitions.
[The following words, terms and phrases, when used in this article, shall have the meanings ascribed to them in this section, except where the context clearly indicates a different meaning:]
Accidental discharge means a discharge prohibited by this article which occurs by chance and without planning or thought prior to occurrence.
Clean Water Act means the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.), and any subsequent amendments thereto.
Construction activity means activities subject to the Georgia Erosion and Sedimentation Control Act or NPDES General Construction Permits. These include construction projects resulting in land disturbance. Such activities include but are not limited to clearing and grubbing, grading, excavating, and demolition.
Illicit discharge means any direct or indirect non-stormwater discharge to the City of Acworth Separate Storm Sewer System, except as exempted in section 50-120.
Industrial activity means activities subject to NPDES industrial permits as defined in 40 CFR, Section 122.26(b)(14).
National Pollutant Discharge Elimination System (NPDES) Stormwater discharge permit means a permit issued by the Georgia EPD under authority delegated pursuant to 33 U.S.C. § 1342(b) that authorizes the discharge of pollutants to waters of the United States, whether the permit is applicable on an individual, group, or general area-wide basis.
The City of Acworth's Separate Storm Sewer System means any facility designed or used for collecting and/or conveying stormwater, including but not limited to any roads with drainage systems, highways, streets, curbs, gutters, inlets, catch basins, piped storm drains, pumping facilities, structural stormwater controls, ditches, swales, natural and man-made or altered drainage channels, reservoirs, and other drainage structures.
Non-stormwater discharge means any discharge to the storm drain system that is not composed entirely of stormwater.
Person means, except to the extent exempted from this article, any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, city, county or other political subdivision of the state, any interstate body or any other legal entity.
Pollutant means anything which causes or contributes to pollution. Pollutants may include, but are not limited to: paints, varnishes, and solvents; petroleum hydrocarbons; automotive fluids; cooking grease; detergents (biodegradable or otherwise); degreasers; cleaning chemicals; non-hazardous liquid and solid wastes and yard wastes; refuse, rubbish, garbage, litter, or other discarded or abandoned objects and accumulations, so that same may cause or contribute to pollution; floatables; pesticides, herbicides, and fertilizers;
liquid and solid wastes; sewage, fecal coliform and pathogens; dissolved and particulate metals; animal wastes; wastes and residues that result from constructing a building or structure; concrete and cement; and noxious or offensive matter of any kind.
Pollution means the contamination or other alteration of any water's physical, chemical or biological properties by the addition of any constituent and includes but is not limited to, a change in temperature, taste, color, turbidity, or odor of such waters, or the discharge of any liquid, gaseous, solid, radioactive, or other substance into any such waters as will or is likely to create a nuisance or render such waters harmful, detrimental or injurious to the public health, safety, welfare, or environment, or to domestic, commercial, industrial, agricultural, recreational, or other legitimate beneficial uses, or to livestock, wild animals, birds, fish or other aquatic life.
Premises mean any building, lot, parcel of land, or portion of land whether improved or unimproved including adjacent sidewalks and parking strips.
State waters means any and all rivers, streams, creeks, branches, lakes, reservoirs, ponds, drainage systems, springs, wells, and other bodies of surface and subsurface water, natural or artificial, lying within or forming a part of the boundaries of the State of Georgia which are not entirely confined and retained completely upon the property of a single person.
Stormwater runoff or stormwater means any surface flow, runoff, and drainage consisting entirely of water from any form of natural precipitation, and resulting from such precipitation.
Structural stormwater control means a structural stormwater management facility or device that controls stormwater runoff and changes the characteristics of that runoff including, but not limited to, the quantity and quality, the period of release or the velocity of flow. (Ord. No. 2005-21, 4-7-2005)
Prohibitions.
Sec. 50-120. Prohibitions.
The following discharges are exempt from the prohibition provision above:
Industrial or construction activity discharges.
Sec. 50-121. Industrial or construction activity discharges.
Any person subject to an industrial or construction activity NPDES stormwater discharge permit shall comply with all provisions of such permit. Proof of compliance with said permit may be required in a form acceptable to the city prior to allowing discharges to the City of Acworth Separate Storm Sewer System. (Ord. No. 2005-21, 4-7-2005)
Portable toilet prohibition.
Sec. 50-122. Portable toilet prohibition.
Access and inspection of properties and facilities.
Sec. 50-123. Access and inspection of properties and facilities.
The city shall be permitted to enter and inspect properties and facilities at reasonable times as often as may be necessary to determine compliance with this article.
Notification of accidental discharges and spills.
Sec. 50-124. Notification of accidental discharges and spills.
Notwithstanding other requirements of law, as soon as any person responsible for a facility, activity or operation, or responsible for emer-gency response for a facility, activity or operation has information of any known or suspected release of pollutants or non-stormwater discharges from that facility or operation which are resulting or may result in illicit discharges or pollutants discharging into stormwater, the City of Acworth Separate Storm Sewer System, state waters, or waters of the United States, said person shall take all necessary steps to ensure the discovery, containment, and cleanup of such release so as to minimize the effects of the discharge.
Said person shall notify the authorized enforcement agency in person or by phone, facsimile or in person no later than 24 hours of the nature, quantity and time of occurrence of the discharge. Notifications in person or by phone shall be confirmed by written notice addressed and mailed to the city within three business days of the phone or in person notice. If the discharge of prohibited materials emanates from a commercial or industrial establishment, the owner or operator of such establishment shall also retain an on-site written record of the discharge and the actions taken to prevent its recurrence. Such records shall be retained for at least three years. Said person shall also take immediate steps to ensure no recurrence of the discharge or spill.
In the event of such a release of hazardous materials, emergency response agencies and/or other appropriate agencies shall be immediately notified.
Failure to provide notification of a release as provided above is a violation of this article. (Ord. No. 2005-21, 4-7-2005)
Violations, enforcement and penalties.
Sec. 50-125. Violations, enforcement and penalties.
In the event the violation constitutes an immediate danger to public health or public safety, the city is authorized to enter upon the subject private property, without giving prior notice, to take any and all measures necessary to abate the violation and/or restore the property. The city is authorized to seek costs of the abatement as outlined in this article.
The city may recover attorney's fees, court costs, and other expenses associated with enforcement of this article, including sampling and monitoring expenses. (Ord. No. 2005-21, 4-7-2005)
Secs. 50-126—50-147. Reserved.
Purpose.
Sec. 50-148. Purpose.
The City of Acworth, Georgia (the "city") is authorized by the supplementary powers provisions of article IX, section II, paragraph III(a)(6) of the Georgia Constitution State Constitution to provide stormwater management services, systems and facilities throughout the geographic area of the city which services, systems and facilities contribute to the protection and preservation of the public health, safety and welfare, and protec-tion of the natural resources of the city. The Federal Clean Water Act places increased emphasis on the role of local governments in developing, implementing, conducting, and making available to its citizens and property owners stormwater management services which address water quality and volume impacts of stormwater runoff. The mayor and the board of aldermen has determined that development in the city to date, and the outlook for continued development at an increasing rate in the future, has created and will continue to create additional needs for stormwater management services, systems, and facilities within the city. (Ord. No. 2022-15, § 1, 6-16-2022)
Findings.
Sec. 50-149. Findings.
Definitions.
Sec. 50-150. Definitions.
The following words, terms and phrases, when used in this article, shall have the meanings ascribed to them in this section, except where the context clearly indicates a different meaning:
Act means and refers to the Clean Water Act as amended by the Water Quality Act of 1987 (33 U.S.C. § 1251 et seq.), as amended, and the rules and regulations promulgated by the United States Environmental Protection Agency pursuant thereto.
Customers of the stormwater utility shall include all persons, properties, and entities serviced by and/or benefiting from the services provided by the city's SWMP and the stormwater utility. These services include, but are not necessarily limited to, the stormwater utility's administration, management, maintenance, expansion, and improvement of the public stormwater management systems for the handling of stormwater runoff of private and public properties, and the regulation of the public and private stormwater management systems, controls, facilities, and activities.
Single family residential property or SFR means improved property containing one residential structure of one or more bedrooms, with bathroom and kitchen facilities, designed for occupancy by one family. A single family residential property may include a "stick-built," industrialized, or manufactured home located on one or more individual lots or parcels of land. Improved property may be classified as a single family residential property even if there is present incidental structures associated with residential uses such as garages, carports, storage buildings, guest houses, servants or caretakers quarters, cottages or barns, or the presence of a commercial use within the residence, as long as such use does not result in additional areas of impervious surfaces. Single family residential properties shall not include improved property containing structures used primarily for nonresidential purposes, manufactured homes located within manufactured home parks where the land is owned by someone other than the owners of the manufactured homes, or multiple dwelling unit residential properties.
Dwelling unit shall mean a structure, which contains one or more bedrooms, a bathroom, and a kitchen facility.
Equivalent runoff unit (ERU) means the statistical median horizontal impervious surface area of a detached single-family residential property within the city as of the date of adoption of this article. The horizontal impervious surface area includes, but is not limited to, all areas covered by structures, roof extensions, patios, porches, driveways, and sidewalks.
Hydrologic response defines the manner and means whereby stormwater collects, remains, infiltrates, and is conveyed from a property. Hydrologic response is dependent on several factors including, but not limited to, the presence of impervious surface, the parcel's size, the parcel's shape, the parcel's vegetative canopy, the parcel's groundwater, the parcel's antecedent moisture and the parcel's geologic condition.
Impervious surface means those areas which prevent or impede the infiltration of stormwater into the soil in the manner in which it entered the soil, in natural conditions, prior to development. Common impervious surfaces include, but are not limited to, rooftops, buildings or structures, sidewalks, walkways, patio areas, driveways, parking lots, storage areas, compacted gravel and soil surfaces, awnings and other fabric or plastic coverings, and other surfaces which prevent or impede the natural infiltration of stormwater runoff which existed prior to development.
Improved property means property altered from its natural state by construction or installation of more than 500 square feet of impervious surfaces.
Non-single family residential property or NSFR means improved property containing multiple dwelling unit residential properties, condominiums, apartments, commercial and office buildings, public buildings and structures, industrial and manufacturing buildings, storage buildings and storage areas, parking lots, parks, recreation properties, tennis courts, swimming pools, public and private schools and universities, research facilities and stations, hospitals and convalescent centers, airports, agricultural uses, water and wastewater treatment plants, and any other form of use not otherwise mentioned which is not a single family residential (SFR), and which has private parking lots and private drives or roads.
Public water influence zone means those areas lying downstream of a culvert, or other stormwater management conveyance system. On the downstream side of the conveyance system, the public water influence zone will extend for a length of six times the diameter (or width) of the culvert from which runoff is being discharged (Field Manual for Erosion and Sediment Control in Georgia, Third Edition, pg. 99), and within the horizontal limits set forth in the aforementioned field manual. For example, if a 48-inch diameter culvert is discharging to a private property, the public water influence zone shall extend 24 feet (six times 48 inches) from the end of the culvert and for the specified width (i.e. typically the width of the creek). The city stormwater utility may perform maintenance and/or capital construction activities only within that portion of the public water influence zone which the city has an ownership interest in, or for which a dedicated easement has been granted to and accepted by the city for such purpose.
Service area means the entire land area within the corporate limits of the city.
Stormwater management services mean all services provided by the city which relate to the:
Stormwater management services may address the quality of stormwater runoff as well as the quantity thereof.
Stormwater management systems and facilities mean those natural and manmade channels, swales, ditches, rivers, streams, creeks, branches, reservoirs, ponds, drainage ways, inlets, catch basins, pipes, headwalls, storm sewers, lakes and other physical works, properties and improvements which transfer, control, convey, detain, retain, treat, or otherwise influence the movement of stormwater runoff.
Stormwater manager means the person appointed by the city manager to administer the provisions of this article.
Stormwater user fee charge means the periodic user fee charge imposed pursuant to this article by the city stormwater utility for providing stormwater management services. This term shall exclude special charges to the owners of particular properties for services, systems or facilities related to stormwater management, including, but not limited to, charges for development plan review, inspection of development projects, on-site stormwater control systems and other stormwater management services provided by the city for which a corresponding fee is collected for the service rendered.
Undeveloped land means land in its unaltered natural condition or which is modified to such a minimal degree as to have a hydrologic response comparable to land in an unaltered natural condition shall be deemed undeveloped. Undeveloped land shall have minimal impervious surface, which impedes the infiltration of stormwater runoff or causes stormwater runoff to collect, concentrate or flow in a manner materially different from what would occur if the land were in an unaltered natural condition. For purposes of this article, undeveloped land includes property altered from its natural condition by the creation or installation of 500 square feet or less of impervious surface.
User is defined as any person who uses property, which maintains connection to, discharges to, or otherwise receives services from the city for stormwater management. (Ord. No. 2022-15, § 1, 6-16-2022; Ord. No. 2023-14, § 1, 4-6-2023)
Stormwater utility and enterprise fund established.
Sec. 50-151. Stormwater utility and enterprise fund established.
Scope of responsibility for stormwater management systems and facilities.
Sec. 50-152. Scope of responsibility for stormwater management systems and facilities.
Stormwater utility customer classes.
Sec. 50-153. Stormwater utility customer classes.
Stormwater user fee charges.
Sec. 50-154. Stormwater user fee charges.
It shall be the policy of the city that user fee charges for stormwater management services to be provided by the stormwater utility in the designated service areas shall be equitably derived through methods which have a demonstrable relationship to the varied demands and impacts imposed on the stormwater management services by individual properties and/or the level of service rendered by, or resulting from, the provision of stormwater management services. Stormwater user fee charge rates shall be structured so as to be uniform within the customer class, and the resultant user fee charges shall bear a substantial relationship to the cost of providing stormwater management services. User fee charge rates shall be in addition to other rates, charges, or fees employed for stormwater management within the incorporated areas of the city, including, but not limited to, plan review and inspection fees, fees for special services, fees in lieu of regulatory requirements, system development charges and special assessments. (Ord. No. 2022-15, § 1, 6-16-2022; Ord. No. 2023-14, § 1, 4-6-2023)
Stormwater user fee charge rates.
Sec. 50-155. Stormwater user fee charge rates.
Stormwater user fee charge exemptions.
Sec. 50-156. Stormwater user fee charge exemptions.
Enforcement methods and inspections.
Sec. 50-157. Enforcement methods and inspections.
Stormwater user fee charge billing, delinquencies, collections, adjustments.
Sec. 50-158. Stormwater user fee charge billing, delinquencies, collections, adjustments.
Failure to receive a stormwater utility bill is not justification for non-payment. The property owner, as identified from public land records of the city, shall be obligated to pay the appropriate stormwater user fee charge for that property.
The stormwater service fee may be billed separately, or on a customer statement and collected along with other fees for services, at the city's sole discretion, provided that in no instance shall the service fee constitute a direct lien against the parcel. Unpaid stormwater service fees shall be collected by filing suit to collect on an unpaid account and by using all methods allowed by state law to collect on any judgment obtained thereby.
A stormwater service fee bill may be sent through the United States mail or by alternative means notifying the customer of the amount of the bill, the date the payment is due, and the date when past due. Regardless of the party to whom the bill is initially directed, the owner of each parcel of developed land shall be ultimately obligated to pay such fee. If a customer is underbilled or if no bill is sent for developed land, the city may backbill for a period of up to one year but shall not assess penalties for any delinquency due to the failure to send a bill or an under billing. A one percent late charge shall be assessed against the owner for the unpaid balance of any stormwater utility service charge that becomes delinquent. (Ord. No. 2022-15, § 1, 6-16-2022; Ord. No. 2023-14, § 1, 4-6-2023)
Appeals, hearings.
Sec. 50-159. Appeals, hearings.