Article 8 — Site Grading, Stormwater Management, Culverts and Piped Drainage Systems and Soil Sediment Control Requirements
Site Grading.
Plan.
feet. Grading plans shall outline the areas which are required to remain undisturbed (i.e., Tree Protection Areas, buffer, etc.) and shall indicate protective fencing or staking to be placed surrounding such areas.
shall be consistent with the River Corridor Certificate approved for the project.
per layer and shall be compacted to a density of 95 percent of the maximum laboratory dry weight per cubic foot as determined by AASHTO Method T-99 in all areas where structure, parking lots and drives, streets, and utilities are to be placed. All other embankments are to be compacted to at least 85 percent.
fall), except as discussed in Section 8.1.6 below. The depth of cut referred to herein shall be the maximum cut or fill occurring in any one section of cut or fill. The slope of cut or fill shall be uniform throughout for each section of cut or fill except when benching is approved by the City. Cut or fill greater than or equal to 2.5:1 (two and a half feet of horizontal run for each foot of vertical rise or fall) shall incorporate a slope drainage bench at every fifteen (15) feet of slope length. Each slope drainage bench shall incorporate a permanent down drain system and be constructed in accordance with the approved standard drawing. When a cut is made in rock that requires blasting, the slope may be steeper if pre-splitting is employed and upon submission of a geotechnical report which substantiates the integrity of the rock in the steeper condition, subject to the review and approval of the City Manager. (Note: No blasting shall occur without a valid permit issued by the Fire Services Division.) Refer to the Standard Plans for grading section and retaining wall details.
shearing resistance and a low cohesiveness. These soils typically are micaceous silts and sandy soils with little or no clay. If the 2:1 slope shows evidence of shearing, non-cohesiveness, sliding, or inability to maintain compaction, the slope shall be stabilized at 3:1 or by using such mechanical methods as needed (such as retaining walls or "grow mats" stapled in place) to maintain slope, height, and integrity.
from the top of a slope to the lowest point of a slope. Sheet flow drainage shall not be allowed to traverse a graded slope.
unless a modification application is approved, zoned for a lot size of less than 12,000 square feet or density of 4 units per acre or more. The intent of this regulation is to ensure adequate lot to lot drainage.
Granting a modification will not nullify the intent of these regulations when the layout has a minimum lot area of 14,520 square feet and minimum lot width of 90 feet. The grading plan may be used as a construction document prior to approval of the Final Plat or as a guidance document for individual lot grading after approval of the Final Plat. The grading plan must include the minimum floor elevations, drainage flow arrows and a designation of slab, basement or slab/basement for each lot.
Stormwater Management.
The Storm Water Management Report shall identify the locations and quantities of storm water runoff entering and exiting the site for both pre- and post-developed conditions.
Analysis of the off-site properties shall anticipate future development in addition to addressing existing conditions.
All culverts, pipe systems, and open channel flow systems shall be sized based on all on-site upstream areas being developed in accordance with the development plans and the off-site upstream areas being fully developed in accordance with the Land Use Plan with no detention. Upstream detention may be included when determining flows, provided the engineer calculates the reduced flows by routing the developed flows through any storm water facility included in the analysis rather than assuming the reduction will occur. The engineer shall show that detention facilities used in the analysis will remain, be properly maintained and the storage volume and outlet structure is based on current conditions.
Detention facilities shall be designed using pre-development flows based on existing conditions for all upstream areas including existing on-site lakes and detention. Post-development flows, except the 100-year flow, shall be based on on-site upstream areas being developed per the development plans and existing conditions for off-site upstream areas. The 100-year flow shall be based on on-site areas being developed per the development plans and the off-site upstream areas being developed per the Land Use Plan with no detention. Upstream detention may be included if it meets the conditions as described for culverts and pipe systems. Existing conditions shall be defined as the conditions of the site at the time of application for a land disturbance permit. The existing condition includes on-site lakes and ponds. Pre-development flows shall be determined by routing the pre-development flows through these storm water facilities. Flows used to size the outlet structures for detention facilities that exceed the 25-year design flow, shall be sized as described for culverts and pipe systems.
When more than 50% of the property of a developed project site is disturbed, the Storm Water Management Report shall be prepared for the entire site and existing impervious areas shall be treated as forest in the pre-developed analysis. When 50% or less of the property is disturbed, detention shall be provided as required by these regulations for the disturbed area and existing impervious areas which are disturbed shall be treated as forest in the pre-developed analysis. For redevelopment, the pre-developed conditions may take into account the existing conditions unless the existing development causes a negative impact on downstream property.
The report shall contain drainage area delineation maps and other exhibits at satisfactory scale and sufficient in quantity and scope to define the boundaries of the site, and off-site areas, relative to watercourses, drainage divides, drainage structures and other pertinent features. The City’s Geographical Information System (GIS) mapping information shall be used where appropriate.
downstream from the project. This area shall extend downstream from the project to a point in the drainage basin where the project area is 10 percent of the total basin area.
The meaning of “overburdened” shall include but not be limited to situations where 25-year velocities exceed the non-erosive velocity of the stream, habitable structures are shown to be subject to flooding for any frequency up to and including the regulatory flood and storm water facilities that can not carry the design storm in accordance with these regulations; and,
Stormwater management is intended to lessen the impacts of urbanization on the natural hydrology of the site. The goal is to reduce the amount of stormwater runoff and pollutants that are released, provide for natural onsite control and treatment of runoff, and optimize the location of stormwater management facilities. These goals are met through runoff reduction or water quality, channel protection, overbank flood protection and extreme flood protection. The hydrologic methodology used to accomplish these goals for any given project shall conform to the Gwinnett County Stormwater Management Manual.
Runoff reduction practices shall be sized and designed to retain the first 1-inch of rainfall on the site to the maximum extent practicable. Runoff reduction practices are stormwater best management practices (BMPs) used to disconnect impervious and disturbed pervious surfaces from the stormwater drainage system to reduce the post-construction stormwater runoff rates, volumes and pollutant loads. Runoff reduction shall be used where practical, prior to using water quality standards. If the runoff reduction requirements cannot be met in whole or part, then the water quality standards shall be used to treat the remainder.
Stormwater management systems shall be designed to detain or treat the runoff from 85% of the storms that occur in an average year and reduce the average annual post-development total suspended solids loadings by 80% in order to meet the water quality requirement. The water quality requirement can be waived if the entire 100% of runoff reduction is provided. Water quality and runoff reduction can also be provided in conjunction in order to meet the water quality requirements outlined in the Gwinnett County Stormwater Management Manual.
Stream channel protection shall be provided using the following three approaches:
24-hour extended detention storage of the 1-year 24-hour return frequency storm event.
Erosion protection measures such as energy dissipation and velocity control.
Preservation of the applicable stream buffer.
Stormwater management facilities shall be designed so that their peak release rates, when combined with those of all bypass areas in the same basin, produce peak flow rates and flow velocities at the site’s boundary line no greater than those which occurred at the same location for pre-developed conditions unless the project meets the conditions specified in Subsection 8.2.2.b.
buffer, landscape strip, or tree protection area, except that natural bottom detention ponds and their appurtenant structures, which require no grading and removal of trees, may encroach into a required construction buffer.
association shall be established for its ownership and maintenance of all stormwater BMP’s within a residential subdivision. All stormwater BMP’s which are placed on an individual private parcel or which crosses multiple private lots must be located within a private drainage easement, which will include access to the right-of-way, to be maintained by the HOA. If the project is provided with an off-site detention facility, a mandatory property owners’ association shall be established for its maintenance. The association’s bylaws shall be recorded concurrently with the recording of a final subdivision plat. The association’s bylaws shall include the same provisions as specified in subsection 5.9.3, Paragraph b. of this regulation.
The following stormwater BMP’s must be located on a separate lot, owned by the HOA, if not located on a recreation area lot as specified in Section 8.2.4.f:
1.Bio-retention Areas
A certified record survey of each facility shall be prepared by an authorized registered professional currently registered in the State of Georgia. A certified record drawing of the facility shall be based upon this survey. The authorized registered professional shall certify that the facility functions hydraulically as designed. Documentation demonstrating the required testing outlined in the Gwinnett County Stormwater Management Manual for the proposed stormwater BMP shall also be provided.
Requirements for a certified record survey and applicable addendum as necessary to the Stormwater Management Report shall be the same for water quality facilities as for stormwater management facilities.
.b When a development uses an existing facility without an existing storm water maintenance bond, the facility shall be cleaned out if necessary and a new record survey, drawing, and certification showing that the outlet structure exists as approved and the flood storage and water quality volume of the facility is equal to or greater that the volume required when the facility was approved. As an alternative, a new record survey, drawing, study and certification showing that the facility meets the development requirements when the facility was approved shall be submitted. The survey shall be performed after substantial completion and stabilization of the project has occurred. The certification and supporting data shall be submitted to the City with the certificate of development conformance and approved prior to issuance of a certificate of occupancy or final plat approval as appropriate.
Culverts and Piped Drainage Systems.
Stormwater conveyance facilities, which may include but are not limited to culverts, storm drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutter, swales, channels, and ditches, shall be provided for the protection of public right-of-way and private properties adjoining projects' sites and/or public rights-of-way. Stormwater conveyance facilities, which are designed to carry runoff from more than one parcel, existing or proposed, shall meet the requirements of these regulations.
Unless otherwise specifically set forth herein or in the City of Sugar Hill Standard Drawings, all of the materials, methods of the construction, and workmanship for the work covered in reference to stormwater conveyance facility construction shall conform to the most recent Standard Specifications of the Georgia Department of Transportation (Georgia DOT). For roads constructed with public funds, either wholly or in part, or roads classified as Major Thoroughfares, materials which meet the Georgia DOT design standards shall be used unless an alternative is specifically approved by the Gwinnett Department of Transportation.
Gutter spread calculations shall be submitted to the City for review and approval prior to issuance of a Development Permit.
Corrugated steel pipe shall have a minimum of 2 ounces per square foot of zinc coating, complying with AASHTO M-218.
These structures shall conform to the requirements of AASHTO M-167.
Fittings supplied by manufacturers other than the supplier of the pipe shall not be permitted without prior approval from City of Sugar Hill.
Reinforced concrete pipe, corrugated steel pipe, corrugated aluminum pipe and corrugated aluminized steel pipe shall be bedded and backfilled in the same manner. Smooth interior corrugated polyethylene pipe shall be bedded and backfilled in accordance with the Georgia DOT Standard Specifications or the Gwinnett County Standard Drawings; in addition, prior to approval of a Final Plat, the City may require the submittal of certification from a mandrel testing agency indicating that all such installed pipe does not exceed 7.5% deflection.
All pipe structures shall be placed on stable earth or fine granular foundation, the characteristics of which would be expected to provide long-term stability. In all live stream pipe installations, in areas of low bearing solid or non-uniform foundations, in area where rock is encountered at the foundation level, or in other locations where conditions warrant, a minimum of 6" of crushed stone bedding is required, (maximum size of stone shall be 3/4").
Geotextiles or geogrids may also be required by the City in problem areas.
Backfill on all pipe installations shall be constructed using foundation backfill material Type I or Type II, as specified in Section 812.01 and 812.02 respectively, in Georgia D.O.T.
Standard Specifications. These materials shall be placed in layers of not more than six inches loose. Compaction of these materials shall be accomplished by hand tamping or machine tamping. Required compaction levels are as follows:
If drainage pipe is installed prior to the completion of grading, a minimum of 4 feet of fill should be provided where needed to adequately protect the drainage structure during the land development phase, unless the structure itself is designed to withstand the anticipated live load during construction.
Headwalls or other end treatments are required on all culverts (except under residential driveways) and at the outlet of all piped collection systems.
Natural bottom arches and box culverts may be used in accordance with the latest Standard Specifications of the Georgia Department of Transportation.
Surface Drainage.
shaped cross-sections are not permitted in grassed channels.
Erosion Control.
Any projects whose permit has lapsed under the terms expressed in Article 4, shall immediately proceed to stabilize all disturbed areas. This responsibility shall fall upon the owner, developer, contractor, or any and all other responsible parties involved in the land disturbance activity.
Except for those activities directly related to compliance with the erosion and sedimentation control ordinance all development activity shall cease while a project is under a stop work order for erosion and sedimentation control violations.
Dams
Any land disturbing activity that involves a property which is proposed to contain a dam shall comply with the provisions of this Article as well as the provisions contained in Article 3, Section 3.1 of these Regulations.
Rules for Dam Safety.
Dams proposed to be 25 feet or more in height and proposed to have an impounding capacity of 100 acre-feet or more at maximum water storage elevation shall be subject to the following:
Dams proposed to be 9 feet or more in height, but less than 25 feet in height, in combination with an impounding capacity proposed to be 20 acre-feet or more at maximum water storage elevation, but less than 100 acre-feet, shall be subject to the following:
Existing dams that are located on a project site and will remain after construction is complete, shall comply with the provisions of this article and all referenced articles as if they were new dams.
When an existing Category II dam may be reclassified to a Category I dam because of a proposed development downstream of the dam, the following shall be provided by the developer for review by the Georgia Safe Dams Program.
Extended Detention
Refer to the Stream Buffer Protection Ordinance of the City of Sugar Hill.
Maintenance requirements shall be as specified in Section 8.2.6 of these regulations.
Reserved.
Stormwater Runoff Quality/Reduction
Stormwater runoff quality/reduction can be provided through runoff reduction, water quality, or any combination of the two. Runoff reduction shall be provided in accordance with the requirements of the Stormwater Management Manual. To the extent Runoff Reduction has been determined to be infeasible for all or a portion of the site, then water quality shall apply for the remaining runoff from a 1.2-inch rainfall event. The design professional shall schedule a meeting with the City when requesting removal or reduction of the runoff reduction requirement.
RRv = 1.0(Rv) As /12 (ft2)
Where Rv = 0.05 + I(0.009)
I = percent impervious cover as a whole number As = On-site area to be treated (ft2)
WQV = 1.2(Rv)As/12(ft2)
Where Rv = 0.05 + I(0.009)
I = Percent Impervious as a whole number As = On-site area to be treated (ft2)
Requirements for a certified record survey and addendum to the Storm Water Management Report shall be the same for water quality facilities as for detention facilities in section 8.2.8.
Where water quality is treated in a regional stormwater management facility approved between April 27, 1999, and January 1, 2001, all lots within the treated area shall either conform to the permit and water quality regulations at the time of approval or conform to the current water quality regulations as stated in section 8.9 A volume verification confirming facility maintenance in accordance with the original design shall be certified by an authorized registered professional and submitted to the City for review and approval.
Where drainage is treated in a regional detention facility approved before April 27, 1999, all lots within the treated area shall conform to the current water quality regulations as stated in section 8.9.1 and current channel protection regulations as stated in section 8.2.3. A volume verification confirming facility maintenance in accordance with the original design shall be certified by an authorized registered professional and submitted to the City for review and approval.
If water quality treatment for a proposed development is to be provided in an existing detention facility, then water quality treatment must be provided for the entire original project basin. A modification to the 25-year detention requirement may be granted for the purpose of retrofitting the stormwater management facility to meet current water quality regulations. Granting of a modification will meet the intent and purpose of these regulations when:
If water quality treatment for a proposed development is provided in an existing water quality facility then water quality treatment conforming to the current regulations must be provided for the entire original project basin.
In order to avoid excessive regulation on individual residential lots, maintenance and repair efforts, and environmental projects, the city’s storm water management exemptions are the same as Gwinnett County Stormwater Management Manual latest edition.
Article 9. Performance Guidelines.