Chapter 400 — Land Development, Article 2 — Grading, Erosion, and Sedimentation
Grading
Chapter 400. Land Development Article 2. Grading, Erosion, and Sedimentation Grading Grading Plan Grading must be done in accordance with the contour lines and grades shown on the approved Grading Plan.
Grading plans must show existing and proposed contour lines at an interval of no more than 2 feet. Grading plans shall outline the areas which are required to remain undisturbed (i.e., Tree Protection Areas, buffers, etc.) and must indicate protective fencing or staking to be placed surrounding such areas.
Grading for roads and improved ditches must be shown.
A grading plan, showing building pad locations, must be submitted for single-family detached dwelling and two-family dwelling subdivisions zoned for a lot size of less than 12,000 square feet or a density of 4 units per acre or more unless a modification application is approved.
Single-family detached dwelling and two-family dwelling subdivision lots must be graded to ensure adequate lot-to-lot drainage. Granting a modification will not nullify the intent of this UDO when the layout has a minimum lot area of 14,520 square feet and a minimum lot width of 90 feet. The grading plan may be used as a construction document before the approval of the Final Plat or as a guidance document for the individual lot grading after approval of the final plat.
Embankments Embankment layering must be consistent with the Gwinnett County Stormwater Management Manual.
Maximum Slopes The maximum slope for cut and/or fill is 2:1 (2 feet of horizontal run for each foot of rise or fall), except: 1) for earthen dam embankments; 2) rock cuts; 3) where certified by a professional geotechnical engineer; or 4) as discussed in paragraph B below.
The maximum slope for earthen dam embankments is 3:1 unless a modification application is approved. The earthen dam embankment slope regulation intends to provide for public safety, soil stability, and dam maintenance considerations.
The depth of cut referred to herein is the maximum cut or fill allowed to occur in any one section of cut or fill. The slope of cut or fill must be uniform throughout for each section of cut or fill unless benching is approved by the City.
Development Maximum slopes must otherwise be consistent with the Gwinnett County Stormwater Management Manual.
Soil Stabilization Special conditions for soil with low shearing resistance and cohesion are required as specified in the Gwinnett County Stormwater Management Manual.
2023
Soil Erosion and Sedimentation Control
Soil Erosion and Sedimentation Control Title This section is known as the "Soil Erosion and Sedimentation Control Ordinance."
Applicability Design standards This section applies when any land disturbance is proposed that requires a permit under this section and continues to apply until the project has been completed.
Abandoned projects Any project whose permit has lapsed under the terms of this UDO must immediately have all disturbed areas stabilized. This responsibility falls upon the owner, developer, contractor, or other responsible parties involved in the land disturbance activity.
Exemption This section applies to any land disturbing activity undertaken by any person on any land, except for the following:
Surface mining, as the same is defined in O.C.G.A. § 12-4-72, "The Georgia Surface Mining Act of 1968."
Granite quarrying and land clearing for such quarrying.
Such minor land-disturbing activities as home gardens and individual home landscaping, repairs, maintenance work, fences, and other related activities which result in minor soil erosion.
The construction of single-family residences, when such construction disturbs less than 1 acre and is not a part of a larger common plan of development or sale with a planned disturbance or equal to or greater than 1 acre and not otherwise exempt under this subsection; provided, however, that construction of any such residence shall conform to the minimum requirements as set forth in O.C.G.A Sec. 12-7-7 and this Paragraph D. For single-family residence construction covered by the provisions of this paragraph there shall be a buffer zone between the residence and any State waters classified as trout streams pursuant to Article 2 of Chapter 5 of the Georgia Water Quality Control Act. In any such stream buffer zone, no land disturbing activity shall be constructed between the residence and the point where vegetation has been wrested by normal stream flow or wave action from the banks of the trout waters. For primary trout waters, the buffer zone shall be at least 50 horizontal feet, and no variance to a smaller buffer shall be granted. For secondary trout waters, the buffer zone shall be at least 50 horizontal feet, but the Director may grant variances to no less than 25 feet. Regardless of whether a trout stream is primary or secondary, for first order trout waters, which are Development streams into which no other streams flow except for springs, the buffer shall be at least 25 horizontal feet, and no variance to a smaller buffer shall be granted. The minimum requirements of O.C.G.A. Sec. 12-7-6(b) and the buffer zones provided by this paragraph shall be enforced by the issuing authority.
Agricultural operations as defined in O.C.G.A. § 1-3-3, “definitions,” to include:
Forestry land management practices, including harvesting; provided, however, that when such exempt forestry practices cause or result in land disturbing or other activities otherwise prohibited in a stream buffer, as established in Sec. 402-2.4.C.15 and Sec. 402-2.4.C.16, no other land disturbing activities, except for normal forest management practices, are allowed on the entire property upon which the forestry practices were conducted for 3 years after completion of such forestry practices.
Any project carried out under the technical supervision of the Natural Resources Conservation Service (NRCS) of the United States Department of Agriculture.
Any project involving less than 1 acre of disturbed area; provided, however, that this exemption shall not apply to any land disturbing activity within a larger common plan of development or sale with a planned disturbance of equal to or greater 1 acre or within 200 feet of the bank of any State waters. For the purposes of this Paragraph H, the term "State waters" excludes channels and drainage ways which have water in them only during and immediately after rainfall events and intermittent streams which do not have water in them year-round; provided, however, that any person responsible for a project which involves less than 1 acre, which involves land disturbing activity, and which is within 200 feet of any such excluded channel or drainage way, must prevent sediment from moving beyond the boundaries of the property on which such project is located and provided, further, that nothing contained herein shall prevent the local issuing authority from regulating any such project which is not specifically exempted by paragraphs A, B, C, D, E, F, G, I, or J of this section.
Construction or maintenance projects, or both, undertaken or financed in whole or in part, or both, by the department of transportation, the Georgia Highway Authority, or the State Road and Tollway Authority; or any road construction or maintenance project, or both, undertaken by any county or municipality; provided, however, that construction or maintenance projects of the department of 2023 transportation or State Road and Tollway authority which disturb one or more contiguous acres of land shall be subject to provisions of O.C.G.A. § 12-7-7.1;
except where the department of transportation, the Georgia Highway Authority, or the State Road and Tollway Authority is a secondary permittee for a project located within a larger common plan of development or sale under the State general permit, in which case a copy of a notice of intent under the State general permit shall be submitted to the local issuing authority, the local issuing authority shall enforce compliance with the minimum requirements set forth in O.C.G.A. § 12-7-6 as if a permit had been issued, and violations shall be subject to the same penalties as violations by permit holders.
Any land disturbing activities conducted by any electric membership corporation or municipal electrical system or any public utility under the regulatory jurisdiction of the Public Service Commission. Any utility under the regulatory jurisdiction of the Federal Energy Regulatory Commission, any cable television system as defined in O.C.G.A. § 36-18-1, or any agency or instrumentality of the United States engaged in the generation, transmission, or distribution of power; except where an electric membership corporation or municipal electrical system or any public utility under the regulatory jurisdiction of the Public Service Commission, any utility under the regulatory jurisdiction of the Federal Energy Regulatory Commission, any cable television system as defined in O.C.G.A. § 35-18-1, or any agency or instrumentality of the United States engaged in the generation, transmission, or distribution of power is a secondary permittee for a project located within a larger common plan of development or sale under the State general permit, in which case the local issuing authority shall enforce compliance with the minimum requirements set forth in O.C.G.A. § 12-7-6 as if a permit had been issued, and violations shall be subject to the same penalties as violations by permit holders; and Any public water system reservoir.
Minimum Requirements General Provisions Excessive soil erosion and resulting sedimentation can take place during land-disturbing activities if requirements of the ordinance and the NPDES general permit are not met. Therefore, plans for those land-disturbing activities which are not exempted by this section shall contain provisions for application of soil erosion, sedimentation and pollution control measures and practices. The provisions shall be incorporated into the erosion, sedimentation and pollution control plans. Soil erosion, sedimentation and pollution control measures and practices must conform to the minimum requirements of Sec. 402-2.5.B and Sec. 402-2.5.C. The application of measures and practices shall apply to all features of the site, including street and utility installations, drainage facilities and other temporary and permanent improvements. Measures shall be installed to prevent or control erosion, sedimentation, and pollution during all stages of any land-disturbing Development activity in accordance with the requirements of this section and the NPDES general permit.
Minimum Requirements/BMPs
§ 12-5-30(f), the "Georgia Water Quality Control Act." As used in this paragraph the terms "proper design" and "properly designed" mean designed in accordance with the hydraulic design specifications contained in the "Manual for Erosion and Sediment Control in Georgia" specified in O.C.G.A. § 12-7-6(b).
Manual for Erosion and Sediment Control in Georgia Adopted The rules and regulations, ordinances, or resolutions adopted pursuant to O.C.G.A.
§ 12-7-1 et seq. to govern land-disturbing activities will require, at a minimum, protections at least as stringent as the State general permit; and best management practices, including sound conservation and engineering practices to prevent and minimize erosion and resultant sedimentation, which are consistent with, and no less stringent than, those practices contained in the Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil 2023 and Water Conservation Commission as of January 1 of the year in which the land-disturbing activity was permitted, as well as the following:
10.Adequate provisions must be provided to minimize damage from surface water to the cut face of excavations or the sloping of fills;
11.Cuts and fills may not endanger adjoining property;
12.Fills may not encroach upon natural watercourses or constructed channels in a manner so as to adversely affect other property owners;
14.Land-disturbing activity plans for erosion, sedimentation and pollution control shall include provisions for treatment or control of any source of sediments and adequate sedimentation control facilities to retain sediments on-site or preclude sedimentation of adjacent waters beyond the levels specified in this section;
15.Except as provided in clause 16 immediately below, there is established a 25-foot buffer along the banks of all State waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action, except where the Director determines to allow a variance that is at least as protective of natural resources and the environment, where otherwise allowed by the Director pursuant to O.C.G.A. § 12-2-8, where a drainage structure or a roadway drainage structure must be constructed, provided that adequate erosion control measures are incorporated in the project plans and Development specifications, and are implemented; or along any ephemeral stream. As used in this provision, the term "ephemeral stream" means a stream: that under normal circumstances has water flowing only during and for a short duration after precipitation events; that has the channel located above the groundwater table year-round; for which groundwater is not a source of water; and for which runoff from precipitation is the primary source of water flow. Unless exempted as along an ephemeral stream, the buffers of at least 25 feet established pursuant to part 6 of Article 5, Chapter 5 of Title 12, the "Georgia Water Quality Control Act," shall remain in force unless a variance is granted by the Director as provided in this clause. The following requirements shall apply to any such buffer:
except where a roadway drainage structure must be constructed; provided, however, that small springs and streams classified as trout streams which discharge an average annual flow of 25 gallons per minute or less shall have a 25-foot buffer or they may be piped, at the discretion of the landowner, pursuant to the terms of a rule providing for a general variance promulgated by the Board of Natural Resources, so long as any such pipe stops short of the downstream landowner's property and the landowner complies with the buffer requirement for any adjacent trout streams. The Director may grant a variance from such buffer to allow land-disturbing activity, provided that adequate erosion control measures are incorporated in the project plans and specifications and are implemented. The following requirements shall apply to such buffer:
2023
Stream Buffer Requirements Nothing contained in O.C.G.A. § 12-7-1 et seq. will prevent any local issuing authority from adopting rules and regulations, ordinances or resolutions which contain stream buffer requirements that exceed the minimum requirements in this section.
Presumption of Violation The fact that land-disturbing activity for which a permit has been issued results in injury to the property of another shall neither constitute proof of, nor create a presumption of a violation of the standards provided for in this section or the terms of the permit.
Application/Permit Process General The property owner, developer and designated planners and engineers must design and review before submittal the general development plans. The local issuing authority must review the tract to be developed and the area surrounding it. They must consult the zoning ordinance, stormwater management ordinance, subdivision ordinance, flood damage prevention ordinance, this section, and any other ordinances, rules, regulations or permits, which regulate the development of land within the jurisdictional boundaries of the local issuing authority. However, the owner and/or operator are the only parties who may obtain a permit.
Application Requirements Application requirements are as follows:
Development
§ 12-7-17(9) or (10) must be submitted in full to the division, regardless of the existence of a local issuing authority in the jurisdiction.
2023
These provisions will not apply unless there is in effect an ordinance or statute specifically providing for hearing and judicial review of any determination or order of the local issuing authority with respect to alleged permit violations.
Plan Requirements
Permits
Inspection and Enforcement Inspection and Enforcement
Secondary permittees will be responsible for the installation and maintenance of best management practices where the secondary permittee is conducting land-disturbing activities. Tertiary permittees will be responsible for installation and maintenance where the tertiary permittee is conducting land-disturbing activities. If, through inspection, it is deemed that a person engaged in land-disturbing activities as defined herein has failed to comply with the approved plan, with permit conditions, or with the provisions of this section, a written notice to comply must be served upon that person. The notice must set forth the measures necessary to achieve compliance and must state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he shall be deemed in violation of this section.
2023
Penalties and Incentives Failure to Obtain a Permit for Land Disturbing Activity Development If any person commences any land-disturbing activity requiring a land-disturbing permit as prescribed in this section without first obtaining said permit, the person will be subject to revocation of their business license, work permit or other authorization for the conduct of a business and associated work activities within the jurisdictional boundaries of the local issuing authority.
Stop Work Orders
Bond Forfeiture If, through inspection, it is determined that a person engaged in land-disturbing activities has failed to comply with the approved plan, a written notice to comply must be served upon that person. The notice must set forth the measures necessary to achieve compliance with the plan and must state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he will be deemed in violation of this section and, in addition to other penalties, shall be deemed to have forfeited their performance bond, if required to post one under the provisions of Sec. 402-2.5.B.6. The local issuing authority may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.
Monetary Penalties 2023 Any person who violates any provisions of this section, or any permit condition or limitation established pursuant to this section, or who negligently or intentionally fails or refuses to comply with any final or emergency order of the Director issued as provided in this section shall be liable for a civil penalty not to exceed $2,500.00 per day. For the purpose of enforcing the provisions of this section, notwithstanding any provisions in any City Charter to the contrary, municipal courts will be authorized to impose a penalty not to exceed $2,500.00 for each violation. Notwithstanding any limitation of law as to penalties which can be assessed for violations of County ordinances, any magistrate court or any other court of competent jurisdiction trying cases brought as violations of this section under County ordinances approved under this section will be authorized to impose penalties for such violations not to exceed $2,500.00 for each violation. Each day during which violation or failure or refusal to comply continues shall be a separate violation.
Education and Certification Persons involved in land development design, review, permitting, construction, monitoring, or inspection or any land-disturbing activity must meet the education and training certification requirements, dependent on their level of involvement with the process, as developed by the Georgia State Soil and Water Conservation Commission in consultation with the division and the stakeholder advisory board created pursuant to O.C.G.A. § 12-7-20.
For each site on which land-disturbing activity occurs, each entity or person acting as either a primary, secondary, or tertiary permittee, as defined in the State general permit, must have as a minimum one person who is in responsible charge of erosion and sedimentation control activities on behalf of said entity or person and meets the applicable education or training certification requirements developed by the Georgia State Soil and Water Conservation Commission present on-site whenever land-disturbing activities are conducted on that site. A project site shall herein be defined as any land-disturbance site or multiple sites within a larger common plan of development or sale permitted by an owner or operator for compliance with the State general permit.
Persons or entities involved in projects not requiring a State general permit but otherwise requiring certified personnel on-site may contract with certified persons to meet the requirements of this section.
If a State general permittee who has operational control of land-disturbing activities for a site has met the certification requirements of O.C.G.A. § 12-7-19(b)(1), then any person or entity involved in land-disturbing activity at that site and operating in a subcontractor capacity for such permittee shall meet those educational requirements specified in O.C.G.A § 12-7-19(b)(4) and will not be required to meet any educational requirements that exceed those specified in said paragraph.
Development Appeals Administrative Remedies The suspension, revocation, modification, or grant with condition of a permit by the local issuing authority upon finding that the holder is not in compliance with the approved erosion, sediment, and pollution control plan; or that the holder is in violation of permit conditions; or that the holder is in violation of any ordinance;
will entitle the person submitting the plan or holding the permit to a hearing before the board of zoning appeals within 30 days after receipt by the local issuing authority of written notice of appeal.
Judicial Review Any person, aggrieved by a decision or order of the local issuing authority, after exhausting their administrative remedies, shall have the right to appeal de novo to the Superior Court of Gwinnett County.
Liability Neither the approval of a plan under the provisions of this section, nor the compliance with provisions of this section shall relieve any person from the responsibility for damage to any person or property otherwise imposed by law nor impose any liability upon the local issuing authority or the Gwinnett Soil and Water Conservation District for damage to any person or property.
The fact that a land-disturbing activity for which a permit has been issued results in injury to the property of another neither constitutes proof of nor creates a presumption of a violation of the standards provided for in this section or the terms of the permit.
No provision of this section permits any persons to violate the Georgia Erosion and Sedimentation Act of 1975, the Georgia Water Quality Control Act or the rules and regulations promulgated and approved thereunder or pollute any waters of the State as defined thereby.
2023 Chapter 400. Land Development Article 3. Environmental Protection Table of Contents
Sec. 403-1. Stream Buffer Protection.............................................................. 400-66 Sec. 403-2. Wetlands ...................................................................................... 400-76 Sec. 403-3. Illicit Discharge and Illegal Connection ........................................ 400-77 Sec. 403-4. Floodplain Protection ................................................................... 400-85