Title 3 — Development and Permitting, Chapter 340 — Inspections
Initiation of Development Activities
Required preliminary erosion and sediment control measures must be installed in the field per the developer's authorized plans and inspected by the Department prior to actual grading or removal of vegetation. All erosion and sediment control measures shall be in place per State and County regulations as soon as or in conjunction with the commencement of activities and in continual coordination with the progress of the project and as per the authorized Erosion, Sedimentation and Pollution Control Plan.
Prior to the initiation of land-disturbing activities and throughout the clearing, grubbing and grading process the following must be accomplished for a designated tree protection area in accordance with any approved Buffer and Landscape Plan or Tree Protection Plan for the property, as set forth in this UDO:
If for any reason a lapse of 14 days occurs after initial land clearing, grubbing, and grading, or development activities have commenced, the developer and/or builder shall be responsible for reestablishing temporary vegetation cover of the site. If the lapse in construction activity extends beyond 30 days, permanent vegetative measures are required under the direction of the Department.
Development Inspections
The developer or contractor shall request all inspections at least 2 business days prior to commencement of any development or construction activity for each of the phases below as authorized by any permit for site work or development. Inspections shall be made by the Department and passed prior to authorization for continuation of further activity or proceeding into new phases. Newly installed underground infrastructure including but not limited to; stormwater pipes and water and sewer lines must be installed per design standards and inspected prior to cover up of any portion.
The following items refer to construction activities that require approval before the next phase of construction occurs:
Notification shall be made by the authorized utility contractor after obtaining a utility construction permit from the Department of Planning and Development.
The completion of inspections by Gwinnett County officials or employees and authorization for work continuation shall not transfer responsibility for the quality of the work performed or materials used from the contractor or developer, nor imply or transfer acceptance of responsibility for project design or engineering from the professional corporation or individual under whose hand or supervision the plans were prepared.