Title 3 — Development and Permitting, Chapter 810 — Stormwater Conveyance Systems
General Requirements
Stormwater conveyance systems, which may include but are not limited to culverts, storm drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutter, swales, channels, and ditches, shall be provided for the protection of public right-of-way and private properties adjoining project sites and/or public rights-of-way. Stormwater conveyance systems that are designed to carry runoff from more than one parcel, existing or proposed, shall meet the requirements of this UDO.
All stormwater conveyance systems design calculations shall be certified by the authorized registered professional (refer to Section 800-20):
Conveyance system design is to be in accordance with the methods contained in the Gwinnett County Stormwater Management Manual. The 100-year ponding limits at and upstream of the culvert shall be shown on the Development Plans and on the Final Plat (if applicable).
Collection System Guidelines
The maximum post-developed flow velocity at the project site's downstream property line with an adjoining tract shall not exceed the maximum pre-developed flow velocity. Calculations shall be required to support this velocity standard.
| Street Classification | Allowable Peak Flow Rate |
|---|---|
| For a 2-Year Storm | |
| Local | 2.0 cfs |
| Minor Collector | 1.0 cfs |
| Other | 0.5 cfs |
contained within a piped drainage system or maintained in a natural watercourse. The stormwater conveyance shall be in a drainage easement.
Walls
every three feet of horizontal, resulting wall height (measured from top of footing to top of wall) will exceed four feet, or surcharge loading will be applied to the back side of the wall, then an appropriate earth retaining structure shall be designed and permitted. The wall may be constructed of concrete, masonry, segmental block or wire basket units, or other appropriate structural materials. Walls that do not exceed six feet in height may also be constructed of timber. Retaining Wall design shall be in compliance with the current Georgia State Minimum Standard Building Code- and ASCE/SEI 7-16. As applicable, wall design shall also comply with ACI 318-18 (Concrete Wall), TMS 402-16 (Masonry Wall), NCMA Design Manual for Segmental Walls (Modular Wall), and/or ANSI/AWC NDS-2018 (Wood Wall). Walls exceeding six feet in height shall be designed and drawings shall be prepared by a Georgia Registered Professional Engineer.
existing or proposed drainage easements, drainage courses, or floodplains. Walls shall be constructed so that the zone of influence from the wall shall not encroach upon the area of potential excavation to maintain, service or replace a utility facility such as stormwater, sanitary sewer, or water facility. Grading on each side of the wall shall be designed so that the wall will not encumber the natural flow of stormwater surface runoff. Walls and wall supports shall be located at a distance from easements to allow for anticipated future maintenance of the easement while still maintaining the structural integrity of the wall.
management must be designed by a Georgia Registered Professional Engineer and must be permitted. Walls shall be designed for hydrostatic loading under full pond conditions and retained backfill soil under dry pond conditions.
The hydrological design must allow for a freeboard dimension and emergency overflow capacity that meets the requirements outlined in the Gwinnett County Stormwater Management Manual. The overflow device should be placed above the projected 100-year flood elevation within the detention area. Detention area and wall calculations are required submittals to Gwinnett County Planning and Development.
sanitary sewer easement must be approved by the utility providing service.