Chapter 7 — Permits, Certificates, Fees and Finances, Article 2 — BUILDING PERMITS
When Required.
No building or other structure shall be erected, moved, extended, enlarged, structurally altered, changed from unfinished to finished space, nor shall any existing or new areas within structures or buildings be covered or concealed by wall coverings, nor shall any grading, excavation or filling of a new lot for the construction of any building or structure be commenced until the department has issued a building permit for such work.
Erosion Control.
A stop work order shall be issued if it is determined by the department and/or the Department of Engineering that the provisions of the Soil Erosion and Sedimentation Ordinance (Ordinance 73) are not being followed.
Sewage Disposal.
No building permit shall be issued for any building or structure unless there is filed with the department a permit from the Forsyth County Department of Environmental Health certifying that the lot has been approved for an individual sewage system according to state regulations and locally adopted codes.
Water Supply.
No building permit shall be issued without evidence of adequate water supply as may be approved by the Forsyth County Department of Environmental Health. No building permit shall be issued for any building or structure unless there is filed with the department proof of purchase of a water meter or installation of a well in areas where water is not available and an on-site well is approved for use.
Land Disturbance Permit.
No building permit shall be issued for a commercial or industrial project or active amenity area for a residential subdivision unless there is an active site development permit for the project, except that an active site development permit shall not be a pre-requisite to the issuance of a building permit in the following circumstances:
New construction shall comply with all existing applicable color and material requirements. This section shall take precedence over section 10-2.2(A).
Application.
Each application to the department for a building permit shall be accompanied by a drawing in duplicate showing:
Egress and Ingress Required.
Where construction is proposed upon a lot or parcel of land not abutting at least sixty (60) feet on a dedicated public street, each application for a building permit on such a lot or parcel of land not shown as a building lot on a subdivision plat approved by the Planning Commission or department shall be accompanied by a true copy of a recorded easement or other document, showing the date and page of recordation in the Clerk's Office, Forsyth County Superior Court, giving the lot or parcel access to a public street.
Without such information, a building permit shall not issue.
False Statement.
Should any person make any false or untrue statement, knowingly or otherwise, to department personnel who cause a building permit to be issued in violation of any provisions of this Code, all permits and certificates shall be void ab initio, and all fees paid by the applicant shall be forfeited without further action by any official.
Deviation from Application.
Should any person cause a building or a structure to be erected in a manner different in size, location, or other characteristic from that represented in the application and accompanying documents, all permits shall be null and void as of the date of the deviation, and any permits or certificates thereafter issued shall be void ab initio without further action by any official.
Report of Deviations.
It is the duty of the owner of the premises and his agent to bring to the attention department personnel or inspectors any deviation from the application and accompanying documents.
Lots in Subdivisions.
No permit or certificate shall be issued involving a building or a structure on a lot or parcel involving a subdivision of land unless and until all applicable requirements of Chapter Eighteen, Subdivisions, and/or Chapter Nineteen, Conservation Subdivisions, as the case may be, are met; provided, however, model home permits may be issued prior to compliance with all applicable requirements of said chapters if the following requirements are met:
Application Review Period.
Building permit application reviews shall be conducted within three
Expiration.
A building permit shall expire twelve (12) months from the date of issuance. Renewal must be made by application within three (3) months of the expiration date and payment of one hundred dollars ($100) to the department. At least one inspection must have been completed and passed prior to renewal of a permit. Renewals shall be limited to one renewal per permit. Should the permit expire after the issuance of a renewal, a new permit must be acquired.